U.S. Army Corps of Engineers · Myrtle Beach Shore Protection Project · Reach 3
Lee Wrenn & Associates, Inc.  Easement Acquisition & Project Management Specialists

Project Home | Sponsors | Corps | Newsletters | Schedule
Illustrations | Photos | Easements | Archive | Contact Us | Other Projects | Home

Project News
Myrtle Beach Shore Protection Project
Surfside Beach · Garden City
Reach 3 November 1998 Vol. III

Project Nears 70% Completion
Resulting In Beautiful Wide Beach Strand
In Garden City and Surfside Beaches

Schedule
Construction nears 70% completion  as the contractor works north in the campground areas north of Surfside Beach.  Construction began the second week in August in Georgetown County at Public Access 26 and progressed north through Garden City and Surfside Beaches. Construction was slated to have begun earlier but was delayed by a shortage of available dredging equipment. The bidding of the project originally attracted only one bidder because of a heavy demand for that type of dredging equipment in the Mississippi River basin due to heavy silting conditions caused by the previous year’s flood conditions. To the delight of area merchants and vacationers  the delayed construction avoided disruptions to the busiest part of the season. Completion is projected for December or early January..

Project Scope
The Reach 3 project encompasses 7.7 miles of shore beginning at the southern end of the Myrtle Beach State Park in Horry County and extending south into Georgetown County to Public Access 26. The initial nourishment is adding  1.7 million cubic yards of sand to the beach. Sand fill is sloped to match the naturally occurring beach profile. Additional fill is being  placed on the beach initially as advanced maintenance. The width of the beach has been increased   75 to 120 linear feet. Sand for the Reach 3 project is coming from a borrow site located approximately 3 miles offshore of Surfside Beach. Sand is vacuumed  from the ocean floor into a hopper dredge until the dredge is full. Hopper dredges were  used because of their ability to take a shallow scoop of fill material from the ocean bottom in order to obtain a consistent high quality fill material. When full, the dredge is taken to a transfer pumping station located in the ocean near shore.  The sand is pumped out of hopper dredge and into a pipeline that goes onto the beach where it is then shaped by bulldozers to the desired profile.

Periodic Renourishment
After the initial construction, the beach  is scheduled for periodic renourishments every 8 years for the 40 year life of the project.  The project is authorized for an additional 10 year cycle if the source of sand is found to be sufficient at the end of the 40 year period.

 

This document was produced by Lee Wrenn, Pres.,
Lee Wrenn  & Associates, Inc., Easement Acquisition Consultant for the Reach 3 Project