Schedule
 

Current Project Events

Public Meetings for Property Owners of Affected Parcels and Other Interested Parties

December 6, 2003 10:00am
Nags Head Board Room
Information meeting for owners of parcels upon which an easement will be required in the Southern Portion of Reach 1
February 14, 2004 10:00am
Kill Devil Hills Town Hall
Information meeting for owners of parcels upon which an easement will be required in the Northern Portion of Reach 1
February 28, 2004 10:00am
Kitty Hawk Town Hall
Information meeting for owners of parcels upon which an easement will be required in the entire Reach 1
 

Projected Construction Schedule

 

Construction

                         Location
Reach 1
Northern Portion
*** Between Prospect Street in Kill Devil Hills and
Sanderlin Street in Kitty Hawk.
Reach 1
Southern Portion
*** Between Isabella Street and Hawks Nest in Nags Head
Reach 2 *** Between  intersection of Old Oregon Inlet Rd. & Hwy 12
and Isabella Street in Nags Head
Reach 3 *** Between Hawks Nest and Blackman Street in Nags Head.
*** Construction dates are subject to the availability of funding.
       Inquiries regarding funding and scheduling should be directed to:
       Sharon Haggett, Senior Project Manager, Wilmington District Corps of Engineers
      
Sharon.F.Haggett@SAW02.usace.army.mil   (910) 251-4441

 Lee Wrenn & Associates, Inc.   P. O. Box 3959,    Kill Devil Hills,  NC   27948    (252) 480-9535